S. 1ST STREET CONSTRUCTION UPDATE: The contractor is on-site today placing all of the shoulder rock needed. They plan to complete this today. They plan to begin placing the mainline asphalt tomorrow.
They hope to get one lane done each day and the shoulder will be paved at the same time as the road. Each lane is getting two lifts (passes) of asphalt, and they are anticipating 4 days total to get all of the mainline paving done. If they don’t have any delays, they should be able to get the mainline all paved by the end of the week.
Next week they plan to come back and complete the tie ins for the entrances and side streets.
The City recommends local traffic only on S. 1st Street the rest of this week. Avoiding S. 1st Street if possible will lessen congestion. Selecting an alternative route will provide you with faster travel to your destination.